Project KPIs: 10 Metrics Worth Tracking (Dashboard Template + Example)
November 21, 2026
Plan Smarter. Execute Faster.
Manage projects on web and mobile. One subscription for your whole team.
Most projects do not fail in one dramatic moment. They drift. A task slips two days, an invoice lands higher than expected, a risk sits open for a month, and by the time anyone notices, the finish date is already gone. Project KPIs exist to make that drift visible while there is still time to act.
This guide explains what project KPIs are, which ten are worth tracking for most teams, how to set them up in five steps, and how to read them each week. It includes a dashboard template you can copy and an illustrative example. It is written for project managers, construction and field teams, healthcare operations leads, and small business owners who want a clear picture of project health without building a reporting department.
What are project KPIs?
A project KPI (key performance indicator) is a number that tells you whether the project is on track against its goals for time, cost, scope, and risk. The important word is "key". A KPI is not every metric you could collect. It is the short list of numbers that someone will actually act on when they move in the wrong direction.
A useful test: if a number turns red and nobody would do anything differently, it is a statistic, not a KPI. Drop it from the dashboard.
Leading vs. lagging KPIs
- Lagging KPIs confirm what already happened, such as budget spent or tasks finished late. They are reliable but arrive after the damage.
- Leading KPIs warn about what is likely to happen, such as a growing count of overdue tasks or open high risks. They give you time to respond.
A good dashboard mixes both, with a bias toward leading indicators during delivery.
10 project KPIs worth tracking
You do not need all ten. Pick the three to six that match the biggest threat to your project, then add others only if they change decisions.
Schedule KPIs
- 1. On-time task completion rate. Tasks finished by their due date divided by tasks due in the period. Easy to calculate and easy for anyone to understand.
- 2. Overdue tasks. The count of open tasks past their due date. This is one of the best early warnings, because overdue work tends to pile up before the finish date moves.
- 3. Checkpoint hit rate. Key checkpoints (inspections, handovers, approvals) met on time divided by checkpoints due. Track the trend over several weeks rather than one result.
- 4. Progress vs. time elapsed. Percent of tasks complete compared with percent of the schedule used. If the project is 50% through its timeline and 30% of the work is done, it needs attention.
Cost KPIs
- 5. Budget used vs. work complete. Compare the share of budget spent with the share of work done. Spending 60% of the budget with 40% of the work finished is a warning sign, even if the total has not been exceeded yet.
- 6. Cost variance (for larger projects). Teams that use earned value can track cost variance (CV = earned value minus actual cost) and the cost performance index (CPI = earned value divided by actual cost). A CPI below 1.0 means each unit of money spent is buying less work than planned. Smaller teams can usually rely on KPI 5 instead.
Risk, issue, and scope KPIs
- 7. Open high risks. The number of risks rated high likelihood or high impact that are still open. A rising count, or a high risk with no owner, is a reason to talk.
- 8. Blocked tasks and issue age. How many tasks are waiting on something, and how long the oldest open issue has been unresolved. Old blockers usually mean a decision is stuck with someone.
- 9. Change requests. The count and total value of approved and pending changes. A growing pending list means decisions are stalling, and a growing approved list means the original plan no longer describes the project.
Team KPI
- 10. Open tasks per person or team. A quick view of workload. If one supervisor holds twelve open tasks and everyone else holds three, the schedule depends on one person's week.
How to set up project KPIs in 5 steps
1. Start from the project goals
Look at the project charter or plan and ask what would make this project a failure. For a clinic move, it might be reopening late. For a fixed-price fit-out, it might be margin. Choose KPIs that watch those outcomes first.
2. Define each KPI in one line
Write the formula, where the data comes from, and who owns the number. "Overdue tasks: open tasks past due date, from the project schedule, owned by the project manager." If two people would calculate it differently, the definition is not finished.
3. Agree green, amber, and red thresholds in advance
Decide before the project starts what counts as fine, what needs watching, and what needs action. For example: overdue tasks green at 0 to 2, amber at 3 to 5, red above 5. Agreeing thresholds early stops long debates about whether a number is "really" bad.
4. Keep the data where the work is
KPIs are only as good as the task data behind them. If due dates, statuses, and expenses are updated in the same place the team already works, the numbers stay current without a separate reporting chore.
5. Review weekly and attach an action to every red
Look at the dashboard at a fixed time, such as the weekly coordination meeting. Every amber or red KPI should leave the meeting with an owner and a response: resequence tasks, add a crew, freeze a scope item, or escalate a decision.
Project KPI dashboard template
Copy this table into a spreadsheet or document. Fill in one row per KPI and update the "This week" column at each review.
| KPI | Formula | Source | Owner | Green / Amber / Red | This week | Status | Action |
|---|---|---|---|---|---|---|---|
| Overdue tasks | Open tasks past due date | Project schedule | [Name] | 0-2 / 3-5 / 6+ | [Value] | [G/A/R] | [Response] |
| Progress vs. time | % tasks complete vs. % schedule used | Project schedule | [Name] | [Your bands] | [Value] | [G/A/R] | [Response] |
| Budget used vs. work complete | % budget spent vs. % work complete | Budget and expenses | [Name] | [Your bands] | [Value] | [G/A/R] | [Response] |
| Open high risks | Count of open high risks | Risk register | [Name] | [Your bands] | [Value] | [G/A/R] | [Response] |
| [KPI] |
Example: week 3 of a retail store fit-out
This is an illustrative example. A small team is fitting out a retail unit over six weeks, with a fixed opening date. At the end of week three (50% of the schedule), the dashboard looks like this:
| KPI | This week | Status | Action |
|---|---|---|---|
| Progress vs. time | 45% of tasks complete, 50% of schedule used | Amber | Review the next two weeks of tasks for anything that can start earlier. |
| Overdue tasks | 4 (all electrical first fix) | Amber | Confirm the electrician's extra day on site, reassign the shelving prep to the carpentry crew. |
| Checkpoint hit rate | 2 of 2 met (strip-out complete, layout approved) | Green | None. |
| Budget used vs. work complete | 48% spent, 45% complete | Green | Watch next week once lighting fixtures are invoiced. |
| Open high risks | 1 (signage permit not yet approved) | Red | Owner to call the council on Monday, prepare temporary signage as a fallback. |
Five numbers, three actions, and one clear priority for Monday morning. Nobody had to read a ten-page report to know where to look.
Common KPI mistakes
- Tracking too many numbers. Twenty metrics on a dashboard means nobody reads any of them. Start small.
- Only tracking lagging indicators. Final cost and final finish date are important, but by the time they move it is too late. Watch overdue tasks and open risks too.
- No thresholds. Without agreed bands, every review turns into an argument about whether a number is acceptable.
- Stale data. If statuses are updated once a month, the dashboard describes last month's project.
- Reds without owners. A red KPI with no named person and no next step is just decoration.
Tracking project health in GanttMaster
GanttMaster is a project management app for the web, iPhone and iPad. Several of the numbers above are visible directly from its existing screens, which keeps the weekly review close to the task data:
- Project cards with a status summary. Each project card shows a progress bar along with total tasks, overdue tasks, and project members, so overdue work and overall progress are visible at a glance across projects.
- Risk, budget, and Stats on the project screen. The project screen shows a Project Risks card (high risks and total risks) and a Budget card (percent used and remaining amount). The per-project Stats screen shows total, completed, and overdue tasks, members, teams, and task progress percentage.
- Gantt bars colored by status. The Gantt chart shows tasks linked with Finish-to-Start, Start-to-Start, or Finish-to-Finish dependencies, with bars colored by task status, so late work stands out in the schedule. Key checkpoints can be added as short checkpoint tasks.
- Status, priority, and owner on every task. Each task carries its dates, assigned user or team, priority, and status, and has its own team conversation on the Tasks screen. When a KPI turns red, the response can be discussed right on the task that needs it.
There is no per-user pricing, so subcontractors, clinic staff, or part-time helpers can update their own tasks and keep the numbers current without counting seats. GanttMaster is free to download with a 1-week trial, then $5.99 a month or $34.99 a year.
Good project KPIs are few, clearly defined, and reviewed on a rhythm. Pick the handful that guard your project's biggest risk, agree what red means before it happens, and make sure every red leaves the meeting with an owner. That is how drift gets caught while it is still small.
Plan it on the web or on your iPhone and iPad
Full disclosure: we make GanttMaster, a project management app for the web, iPhone and iPad with FS/SS/FF dependencies, tasks and subtasks, checkpoint tasks, a Today view with reminders, team assignment, risk and budget tracking, and no per-user pricing. Start with a 1-week free trial on the web or in the app, then $5.99/month or $34.99/year.