Float in Project Management: Total Float vs Free Float (With Example)

November 23, 2026

GanttMaster

Plan Smarter. Execute Faster.

Manage projects on web and mobile. One subscription for your whole team.

Every schedule has tasks that must happen exactly on time and tasks that can wait a little. The difference between them is called float (or slack). Knowing where it sits tells you which delays are harmless and which ones push the finish date.

This guide explains what float is, the difference between total float and free float, how to calculate both with a forward and backward pass, what negative float means, and how to manage float without fooling yourself.

What is float in project management?

Float is how long a task can be delayed before it causes a problem. "Slack" means the same thing. There are two kinds:

  • Total float is how long a task can slip without delaying the project finish date (or a required end date).
  • Free float is how long a task can slip without delaying the early start of any task that follows it.

Tasks with zero total float form the critical path: the chain that sets the finish date. See our guide to the critical path method.

Total float vs free float

The two numbers answer different questions, and confusing them is a common scheduling error.

Total floatFree float
ProtectsThe project finish dateThe next task's early start
FormulaLate start minus early start (or late finish minus early finish)Earliest early start of successors minus this task's early finish
Shared?Often shared by a whole chain of tasksBelongs to that task alone
Safe to use?Only if you know who else is counting on itYes, nobody else is affected

Free float is always equal to or smaller than total float. When a chain shares float, using it early removes it from the tasks further down.

How to calculate float: forward and backward pass

You need three inputs: a task list, a duration for each task, and the dependencies between them. Our guide to task duration estimation covers the second one. Then:

  1. Forward pass. Start the first task at day 0. For each task, early start (ES) is the largest early finish of its predecessors, and early finish (EF) is ES plus duration. The last EF is the project duration.
  2. Backward pass. Set the late finish (LF) of the last task to the project duration. Work backwards: late start (LS) is LF minus duration, and a task's LF is the smallest LS of its successors.
  3. Total float = LS minus ES.
  4. Free float = the smallest ES of the task's successors minus its own EF.

This uses the "end of day" convention: EF 2 means the task finishes at the end of day 2, and a successor with ES 2 starts on day 3.

Worked example: a small office lighting and data upgrade

Here is an illustrative field crew job with invented durations, purely as an example. A crew is upgrading lighting and network cabling in a small office, plus fitting new signage. All links are finish-to-start, durations are in working days.

#TaskDaysDepends onESEFLSLFTotal floatFree float
ASite survey and order materials2None020200
BMaterials delivery (waiting time)5A272700
CStrip out old fittings3A254722
DRun new cabling4B, C71171100
EOrder and receive signage3A25101380
FInstall fittings and test3D1114111400
GFit signage1E56131488
HClient walkthrough and handover1F, G1415141500

Forward pass

A runs from 0 to 2. B, C and E can all start after A, so their ES is 2. Cabling (D) needs both delivery and strip out, so its ES is the larger EF: 7 from B, not 5 from C. F follows at 11 to 14. Handover (H) waits for F (14) and G (6), so it starts at 14 and the project takes 15 days.

Backward pass

H must finish by 15, so F and G must finish by 14. G's LS is 13, so E can start as late as 10. D must finish by 11, so it starts by 7, and both B and C must finish by 7. A's LF is the smallest LS of B (2), C (4) and E (10), so 2.

What the numbers tell you

  • Critical path: A, B, D, F, H. All have zero total float: if delivery slips a day, so does handover.
  • Strip out (C) has 2 days of total float and 2 days of free float. The crew can start it two days late without affecting anyone.
  • Signage (E) shows the trap. It has 8 days of total float but zero free float, because its float is shared with G. If E finishes 3 days late, G starts 3 days late and the chain has only 5 days left.
  • Fitting signage (G) owns the 8 days as free float, since its only successor is the handover.

What is negative float?

Negative float appears when a task's late dates fall before its early dates. It happens when a required date is earlier than the logic allows, or progress falls behind. In the example, if the client insists on handover at the end of day 13, the backward pass starts from 13 instead of 15, and every task on the critical path shows minus 2 days of total float.

Negative float is not a calculation error. It is the schedule telling you, early and in numbers, that the plan cannot hit the date as drawn. The fix is a decision: overlap tasks where the work allows (a start-to-start link instead of finish-to-start), add crew, cut scope, or move the date. Our guide to FS, SS and FF dependencies shows when overlapping is realistic.

How to use float to manage a schedule

Spend free float first

When a task needs to slide, look for free float before touching anything else. In the example, starting strip out two days late costs nothing downstream.

Treat shared total float as a team budget

Total float along a chain belongs to the chain, not to the first person who uses it. Agree on who may consume it, and say so out loud when it is used: "Signage ordering slipped 3 days, 5 days of float left on that chain."

Protect float near the end

Late float is often the only cushion before handover, so do not fill it with extras. A short checkpoint task before the handover is a useful place to stop and check how much cushion remains.

Do not hide float

Padding every duration so float disappears makes the schedule look safe but removes the information you need. Keep estimates honest and let float show where it really is.

Recheck after every update

Float changes whenever a task finishes early or late, or a link changes. Review it in your weekly update, alongside your project timeline.

Common float mistakes

  • Reading total float as free float. Using a task's total float can delay its successors and eat float someone else planned on.
  • Missing dependencies. A task with no successor appears to have huge float. Usually it simply is not linked to anything.
  • Forgetting waiting time. Delivery, curing, approvals and inspections take calendar days. Leave them out and the float you see is not real.
  • Ignoring negative float. It does not fix itself. The earlier you act, the cheaper the fix.

Float checklist

  • Every task has a duration, including waiting time.
  • Every task (except the last) has at least one successor, and every task (except the first) has a predecessor.
  • Forward and backward pass done, critical path identified.
  • Total and free float noted, shared chains given an owner.
  • Any negative float discussed and a decision recorded.
  • Float reviewed in every weekly update.

Seeing float in GanttMaster

GanttMaster is a project management app for the web, iPhone and iPad, made by our team. A linked Gantt chart lets you see float directly:

  • Enter tasks with dates. Add tasks and subtasks with start and end dates at their early dates, a priority, and an assigned user or team.
GanttMaster task details screen with task title, description, start date and end date, and assigned user and team
Example project: task details with start and end dates and assignment.
  • Link them. Open a task, go to the Dependencies tab, choose Add Dependency, pick the type (Finish-to-Start, Start-to-Start, Finish-to-Finish or Start-to-Finish) and use Select Task to choose the linked task.
GanttMaster Dependencies tab with Add Dependency options Finish-to-Start, Start-to-Start, Finish-to-Finish and Start-to-Finish
Example project: choosing a dependency type in the Dependencies tab.
  • Read the gaps. In the Gantt view, the space between the end of a bar and the start of the next linked bar is that task's free float. Bars that butt directly against their successors all the way to the end form the critical chain.
  • Mark the cushion. Add a short checkpoint task before handover, with a dependency on the last critical task, so the team can see how much room is left.
GanttMaster Gantt chart with task bars across daily dates and dependency lines linking tasks
Example project: Gantt chart with dependency links. Gaps between linked bars show slack.

From there, the Today view with reminders keeps critical tasks in front of the right people, risk tracking gives negative float an owner and a mitigation plan, and there is no per-user pricing, so the whole crew can update their own tasks. You can start with a 1-week free trial, then $5.99 a month or $34.99 a year.

Know where your slack is

Float is not spare time, it is information. Calculate it with a forward and backward pass, use free float first, treat shared total float as a team budget, and act on negative float as soon as it appears. Swap your own tasks into the office example and you will know which delays you can absorb.

GanttMaster logo

Plan it on the web or on your iPhone and iPad

Full disclosure: we make GanttMaster, a project management app for the web, iPhone and iPad with FS/SS/FF dependencies, tasks and subtasks, checkpoint tasks, a Today view with reminders, team assignment, risk and budget tracking, and no per-user pricing. Start with a 1-week free trial on the web or in the app, then $5.99/month or $34.99/year.

Download on the App Store

Prefer your browser? Sign up on the web