Issue Log: How to Track and Resolve Project Issues (Template + Example)
November 18, 2026
Plan Smarter. Execute Faster.
Manage projects on web and mobile. One subscription for your whole team.
Every project runs into problems. A delivery arrives short, a permit is delayed, a supplier changes a price, or two teams discover they planned to use the same room on the same day. What hurts projects is the problem that everyone mentions in a meeting and nobody owns afterwards.
An issue log fixes that. It gives every problem a number, an owner, a next action, and a date, so it gets resolved instead of discussed. This guide explains what an issue log is, how it differs from a risk register, which fields to include, how to run one in six steps, a template you can copy, and an illustrative example. It is written for project managers, construction and field teams, healthcare operations leads, and small business owners.
What is an issue log?
An issue log (also called an issue tracker or issues register) is a list of problems that are affecting the project right now, along with who is handling each one and what happens next. It is a working document. Items are added as soon as they are raised, reviewed regularly, and closed when they are resolved, with a short note on how.
An issue is anything that is already blocking or harming the work: a task that cannot start, a deliverable that failed inspection, a cost that has gone over plan, or a decision that is holding up the team.
Issue log vs risk register
The two are related but answer different questions:
| Risk register | Issue log | |
|---|---|---|
| Deals with | Things that might happen | Things that have already happened |
| Main question | How likely is it, and how bad would it be? | How urgent is it, and who fixes it? |
| Typical action | Mitigation plan, prepared in advance | Next action with a due date |
| Example | "The tile supplier may deliver late" | "The tiles arrived in the wrong color" |
When a risk actually happens, it moves from the risk register to the issue log. When an issue reveals a new danger for the rest of the project, add that danger to the risk register. Keeping both lists side by side means nothing falls into the gap between them.
What to include in an issue log
Keep the log short enough that people actually fill it in. These fields cover most projects:
- ID. A short reference such as ISS-01, so people can refer to it in meetings and messages.
- Date raised and raised by. When the issue was logged and who reported it, in case you need more detail.
- Description. One or two clear sentences on what is wrong. "Plumbing problem" is too vague. "Floor drain in the kitchen is 4 cm off the drawing position" is useful.
- Category. For example schedule, cost, quality, supplier, people, or approvals. Categories help you spot patterns later.
- Impact. What it affects: which tasks are blocked, how much it may cost, or which date is at stake.
- Priority. High, medium, or low, based on impact and urgency.
- Owner. One named person or team responsible for getting it resolved.
- Next action and due date. The very next step, and when it must be done.
- Status. Open, in progress, waiting (on someone outside the team), or closed.
- Resolution and date closed. What fixed it and when.
How to run an issue log in 6 steps
1. Make it easy to raise an issue
If logging a problem takes ten minutes, people will mention it in passing instead. Agree on one place for the log and tell the whole team, including subcontractors or part-time staff, that anyone can add an item.
2. Triage within a day
Each new issue needs a quick review, ideally the same day. Is it really an issue, or a question, a change request, or a risk? If it is an issue, give it a category and a priority. A practical rule: high means it is blocking work now or threatens a key date, medium means it will cause trouble soon if nothing is done, and low means it should be fixed but can wait.
3. Assign one owner and a next action
"The team" cannot own an issue. One person or one named team does. Write down the next action, not the whole solution: "Call the supplier and confirm the replacement delivery date" is a next action. Add a due date so slow issues become visible.
4. Link the issue to the work it affects
An issue matters because of what it blocks. Note which tasks cannot start or finish until it is resolved. This is where your schedule helps: if the issue sits in front of a task with dependencies, every task after it is affected too.
5. Review open issues on a fixed rhythm
Go through open issues at every regular team meeting, starting with the high-priority ones. For each item, ask three questions: what has happened since last time, is the next action still right, and is the due date still realistic? Escalate anything the team cannot resolve on its own. If fixing an issue changes scope, budget, or dates, raise a formal change request rather than quietly adjusting the plan.
6. Close issues properly and keep the record
Close an issue only when the problem is actually resolved, not when someone has promised to fix it. Write one line on how it was resolved and the date. Keep closed items on the log. They show which categories caused the most trouble, useful input for the next project.
Issue log template
Copy this into a spreadsheet, a document, or your project tool:
| ID | Raised (date, by) | Description | Category | Impact | Priority | Owner | Next action | Due | Status | Resolution (date) |
|---|---|---|---|---|---|---|---|---|---|---|
| ISS-01 | Open | |||||||||
| ISS-02 | Open |
Add a header with the project name, who maintains the log, and the date it was last reviewed.
Example: an issue log for a small restaurant kitchen fit-out
The example below is illustrative, written for a fictional small business, to show how the fields work together.
A restaurant owner is refitting the kitchen over four weeks while the dining room stays closed. The contractor's site lead maintains the issue log and reviews it with the owner every Monday and Thursday.
- ISS-01, high, in progress. The floor drain is 4 cm off the position on the drawing, so the new dishwasher cannot be placed. Impact: blocks dishwasher installation and the plumbing inspection. Owner: plumber. Next action: confirm whether the drain can be moved or the dishwasher position adjusted, due Wednesday.
- ISS-02, high, waiting. The extraction hood is delayed by the supplier. Impact: the electrician cannot finish wiring above the cooking line. Owner: site lead. Next action: get a confirmed delivery date in writing, due Tuesday. This was on the risk register as "hood delivery may slip", so the mitigation (a fallback supplier quote) is ready to use.
- ISS-03, medium, open. The wall tiles delivered are a slightly different shade from the sample. Impact: a quality issue, not yet blocking because tiling starts next week. Owner: restaurant owner. Next action: decide whether to accept or return the batch, due Friday.
- ISS-04, closed. The site key was not handed over on day one, so the team started half a day late. Resolved: the landlord provided a second key the same afternoon.
At the Thursday review, the team sees that ISS-01 and ISS-02 both block tasks that the final inspection depends on. Those two get the owner's attention first, and the tile decision can wait a few days without harm.
Common issue log mistakes
- Logging without owners. An issue with no owner is just a complaint written down.
- Everything is high priority. If every item is high, the label means nothing. Be honest about what can wait.
- No review rhythm. A log that is not reviewed becomes a list of old problems.
- Mixing issues with risks or change requests. Keep each in its place, and move items between them when needed.
Tracking project issues in GanttMaster
An issue log works best when it sits next to the schedule and the team, not in a separate file. GanttMaster is a project management app for iPhone and iPad, and you can run your issue log inside the project itself:
- Log each issue as a task. Give it a clear title, a description, start and end dates, a priority, and an assigned user or team. You can keep all issues under one parent task with subtasks, so the log stays in one place.
- Discuss each issue in its own conversation. Every task has its own comments on the Tasks screen, so updates on an issue stay with that issue instead of getting lost in group chats. File links can be added for photos, quotes, or drawings, and notifications keep the owner and the team up to date.
- Connect the issue to the work it blocks. Add a Finish-to-Start dependency from the issue task to the blocked task, and the Gantt chart shows the chain. Bars are colored by status, so problem areas stand out.
- See open problems at a glance. Project cards show a progress bar with total tasks, overdue tasks, and members, and the Stats screen shows total, completed, and overdue tasks for each project.
- Keep risks and costs alongside issues. The risk module records likelihood, impact, mitigation, owner, and due date, and budget tracking lets you record the extra expense an issue causes and see the remaining budget.
There is no per-user pricing, so the site lead, the subcontractors, and the owner can all be on the project without counting seats. GanttMaster is free to download with a 1-week trial, then $5.99 a month or $34.99 a year.
An issue log does not need to be elaborate. It needs a clear description, one owner, a next action, a date, and a team that reviews it every week. Do that, and problems get solved while they are still small.